Preparing for Your Flex Server Replacement

Basic migration schedule **Subject to change

Timeline

Description of Events

Involved Parties

Prior to Migration Week

New server access and prep

Agency IT and MSI SA

Day 1 of Migration Week

1-4 hours* of downtime. Users log back in on the source server. Data is transferred and loaded onto the destination server 1-6 hours* of downtime. Transaction logs from the previous day are transferred and loaded onto the destination server. Users log in on the destination server. Interfaces are brought over.

Agency IT/SAA and MSI SA

Day 2 of Migration Week

Agency IT/SAA and MSI SA

Remainder of Migration Week Interface and issue troubleshooting

Agency IT/SAA and MSI SA

Following the Completion of the Migration

Transition back to regular support

Agency SAA and MSI Support